How to Hand Over a Project When Someone Leaves: Steps That Keep the History and the Promises from Getting Lost

Published:

How to hand over a project when someone leaves

Two weeks after taking over a project, the new owner gets this email from the client.

“Your predecessor told us that you would make small fixes free of charge for one month after launch.”

The files and the task list had all been handed over properly. But that promise was not written down anywhere.

Someone leaves the company, moves to another team or takes a long leave. Sooner or later, every team has to change who is in charge of a project.

Files and task lists are easy to hand over. But the history of why things were decided, and the promises made to the client in conversation, easily get lost. This article covers what tends to get lost in a handover, how to run the handover as a task, and what you can do in everyday work to be ready.

Key takeaways

  • What gets lost in a handover is not the files but the history and the promises.
  • Make the handover a task for each project, and let the person taking over mark it as done.
  • If you record decisions and promises as you go, a handover only means showing where the records are.

Note: this article is written by the developer of GeckoFlag.

What gets lost in a handover

When we think of a handover, we tend to think of passing on files and accounts. But things you can point to are handed over fairly well. What slips is what existed only in that person’s head.

Easy to hand over Easy to lose
FilesThe history of why things were decided
The task listPromises made to the client in conversation
ContractsThe client’s preferences and how they like to communicate
The scheduleThe mood of the conversations in progress
The list of accountsWhere everything is

Everything in the right column is something the person could tell you if asked, but has never written down. To the previous owner, these things feel so obvious that they may not even realize they need to be handed over.

Take “the mood of the conversations in progress.” The client may be a little unhappy with the latest revision. The client’s contact may be struggling to win over people inside their company. You can’t tell this from the text of the emails alone. If the new owner writes in their usual tone without knowing it, they may meet unexpected pushback.

“Where everything is” works the same way. Where in the shared folder is the latest design file? Which email contains the important agreement? The previous owner uses these every day and never gets lost, but the new owner has to search from scratch.

When a spoken promise slips, as in the opening scene, the client sees it as “they don’t keep their word.” The new owner means no harm, but trust is shaken.

What a handover really needs to pass on is not the files, but the history and the promises.

Run the handover as a task

Handovers often end with a rushed talk just before the last day. Instead, make the handover itself a task and move it forward like any other work.

  1. Create a “Handover” task for each project: list the items to check inside it. Use the template in the next section for the items.
  2. Set the due date before the last day: this gives the previous and new owners time to work together. If the due date is the last day, the handover ends before anyone can check it.
  3. Assign it to the new owner: the previous owner writes it, but the person who checks it and marks it as done is the one taking over.
  4. The person taking over marks it as done: don’t let the person handing over finish with “I handed it over.” It is done when the new owner has read it and finished asking about anything unclear.

Example: starting two weeks before the last day

  • Two weeks before: create a “Handover” task for each project and assign it to the new owner
  • Week 1: the previous owner fills in the items, and both send the client a note about the change together
  • Week 2: the new owner checks things while actually running the project, and asks about anything unclear
  • Before the last day: once the new owner is satisfied, they mark the handover task as done

The rule that the person taking over marks it as done looks small, but it works. The person handing over tends to feel their job is finished once they have written things down. When the reader decides whether it is done, “written but not understood” is less likely to remain.

What to write in a handover

Write the following items in the handover task. You can use the item names as they are, so fill them in for each project.

Item What to write
Where the project standsWhat stage it is at now. What the next step is
Tasks in progressThings waiting for a reply, things due soon
Client contactsWho to contact, and how. How they like to be contacted (email rather than phone, for example)
Promises made in conversationEvery promise that is not in the records
Things to watch out forPast trouble, requests that tend to change
Where the files areWhere the latest versions are
Where the accounts areWhich service accounts exist, and where they are managed
MoneyAnything not yet invoiced, not yet paid, or still being quoted

The most important item is “Promises made in conversation.” Ask the previous owner directly: “Are there any promises that aren’t written in emails or tasks?” Without being asked, people often can’t remember them.

Under “Where the accounts are,” write only where each account is managed. Never write passwords or login details themselves in a task or the wiki. Hand over passwords separately, in the way your company has decided to manage them.

How to tell the client about the change

A change in who handles their project worries the client too. Cover these three points when you tell them.

1Contact the client together

Send the note about the change from both the previous and the new owner, or attend a meeting together. When the previous owner introduces the new one, the client feels comfortable talking to them.

2Give the date of the change and the contact until then

Tell them, with dates, who will be in charge from when, and who to contact until then. If you leave this vague, the client may send the same message to both of you, or to neither.

3Keep responding during the handover

Being in the middle of a handover is no excuse for slow replies. Write anything waiting for a reply under “Tasks in progress” in the handover task, and decide which of you will reply.

For example, the note about the change can include the following.

Example note about the change

  • Who will be in charge, and from what date
  • That the previous owner remains the contact until then
  • The work in progress, and what you will get back to them about next
  • That the promises made so far (such as the scope of fixes after launch) have been passed on to the new owner

The last line is especially effective. When the client knows the promises have been passed on, they don’t have to explain everything again from the start. And if you and the client remember a promise differently, you find out before the change.

After the handover

A handover doesn’t end on the last day. Most gaps are found after the new owner actually starts running the project.

  • Agree on how long the new owner can ask the previous owner questions: if the person is leaving, until the last day. If they are moving to another team, something like “you can ask questions for one month after the move.”
  • When you find a gap, add it to the handover task: don’t stop at hearing the answer. Record it in the task.
  • Ask the previous owner in comments on the handover task, too: answers given in chat get buried. If you ask in a task comment, the questions and answers become part of the handover record, and nobody has to ask the same thing twice.
  • What you add also helps the next person: the same project may be handed over again someday. When that happens, what you added this time will help as it is.

What you can do in everyday work

The best way to make handovers easy is not to try harder during the handover. It is to keep a record of the history and the promises as you go.

  • Record decisions and their reasons in tasks: just one line, such as “We chose C, because…,” lets the new owner find out for themselves why things are the way they are.
  • Write spoken promises to clients in a comment the same day: record what was decided in a meeting or on a call while it is still fresh.
  • Once a month, look for things only you know: when you find one, write it in a task or the wiki.

If you keep records as you go, a handover only means showing where the records are. You can’t always know in advance when someone will take over. Even with a sudden absence, records let others keep the project moving.

Whether someone is leaving, moving to another team or taking a long leave, the handover is the same. The only difference is whether you can still ask the previous owner questions afterward. The less you can ask, the more you depend on the records kept in everyday work.

RelatedHow to record decisions as tasks is covered in Part 2 of the series “Task Management for Teams Working with AI,” “Frame Tasks Around What to Decide, Not Just What to Make,” and how to record why you chose an option is covered in Part 4, “AI Drafts Are Decision Material, Not Finished Work”

Putting it into practice in GeckoFlag

Finally, here is how to apply this approach in GeckoFlag.

  • Make “Handover” a parent issue: create a “Handover” issue in the project, and list the items to check as child issues (parent and child issues can go two levels deep, within the same project). Assign it to the new owner who is taking over.
  • Reassign issues in progress to the new owner: change the assignee issue by issue. You can also change the assignee and status at the same time as posting a comment.
  • Trace the history through comments: issue comments keep a record of the conversation along with changes made at the time, such as status changes. The new owner can read them to follow the history.
  • Summarize the project and things to watch out for in the wiki: if you write the contacts, the client’s preferences and things to watch out for in each project’s wiki, anyone who takes over only needs to look in the same place.
  • Move project ownership to the new owner first: a user who is the owner of a project can’t be deleted as is. Before deleting the account, move ownership to the new owner.

When you delete the account of someone who has left, the issues and comments they wrote remain. However, their name shows as “Not set,” which makes it harder to tell who wrote what. While you still need to trace the history, keep this in mind when deciding, for example by not rushing to delete the account. Also, if that person is the only administrator, the last remaining administrator can’t be deleted or have their role changed, so make someone else an administrator first.

When you delete an account, any screens where that user was logged in on other devices are logged out at their next action (v1.9.5 or later). The steps for adding and deleting users are in the manual under “Adding & Editing Users” and “Permissions by Role.”

You can try parent and child issues and the wiki in the demo.

Summary

  • What gets lost in a handover is not the files, but the history and the promises made to the client
  • Make the handover a task for each project, set its due date before the last day, and let the new owner mark it as done
  • Ask the previous owner directly about promises made in conversation, and write them down. Never write passwords
  • Recording decisions and promises in everyday work is the best preparation for a handover

You never know when someone will need to take over. Start by writing down one line about what you decided today.